Milestone Team/Group
Milestone 1: Verify Analog Electronics from ECEn 340 and Implement a Queue Library Module Team
Milestone 2: Complete MATLAB Modeling of the Laser-Tag System Team
Milestone 3: Implement All Software and Demonstrate a Feedback Configuration (on ZYBO board only) Team
Milestone 4: Integrate Analog Electronics with ZYBO board and Demonstrate Working System at 40 Feet Group
Milestone 5: Demonstrate the Fully-Packaged Laser-Tag System Group
Milestone 6: Creative Project: Augment or Modify the Laser Tag System Group